Dawn Way Area Improvements

The City of Inver Grove Heights is in the construction phase of the Dawn Way Area Street Rehabilitation project for 2023. This project webpage maintains general information. You can receive timely email construction-related updates by signing up with the Dawn Way project on the following "Notify Me" link.

Tentative Project Timeline

  • Improvement Hearing, Order Plans, and Specifications (City Council Meeting Item): October 24, 2022
  • Approve Plans and Specifications, Authorize Bidding (City Council Meeting Item): December 12, 2022
  • Award Contract and Approve Budget (City Council Meeting Item): March 13, 2023
  • Construction: April through October 2023
  • Assessment Hearing (City Council Meeting Item): October 23, 2023

Meetings & Project Documents

Stay Connected

Email Notifications

Sign up for the "Notify Me" subscriber list for this project to receive updates on project progress and scheduling.

Questions

Project staff appreciates your patience during the construction of this project. These are large neighborhood projects with unique pavement conditions. If you have questions or concerns, please feel free to contact either the City's Construction Inspector or Assistant City Engineer via the contact info below.

  • Construction Inspector, Senior Engineering Technician Nick Hahn at 651-470-6767 or Email Nick Hahn
  • Project Manager, Steve Dodge at 651-450-2541 or Email Steve Dodge