2024 Proposed Pavement Management Initiative Project Areas

Planning has begun for the 2024 pavement rehabilitation projects. The proposed project areas and maps, along with future details for neighborhood meetings, can be found below by opening the project tab. You can also subscribe to receive emails on project notifications.

If you don’t see your neighborhood included on this project list, check back! City leadership is making a long-term commitment to road improvements. An ambitious project pace will continue every year until we improve city roads to the condition we all want them in. View the five-year rehabilitation tab on the road construction map.

2024 Project Plans

  1. 96th Street & 99th Street

96th Street (Project #2024-09H)

Project Introduction Letter to Residents (PDF)

99th Street (Project #2024-09J)

Project Introduction Letter to Residents (PDF)

After further study into the 96th and 99th Street projects, it was determined that combining these two streets repair projects into one would benefit residents through increased efficiencies and economies of scale.  

Sign up for project notifications

See a map of the project area (PDF)

Project Timeline

  • Data Collection & Information Gathering: Summer 2023
  • Feasibility Study Open House - All are welcome!

    Wednesday, Sept. 13,  5 p.m. to 7 p.m.

    Veterans Memorial Community Center, West Arena

    8055 Barbara Avenue

    2024-09H 96th and 99th Street Map (PDF)
    2024-09H 96th Street and 99th Street Area Costs - Funding Board (PDF)
    CP 2024-09H Assessment Roll (PDF)

  • Public Hearing at City Council Meeting - Feasibility Report & Approve Project - All are welcome!

    Monday, Sept. 25, 6 p.m.

    IGH City Hall, Council Chambers

    8150 Barbara Avenue


  • Final Design: Fall 2023-Spring 2024
  • Pre-Construction Open House: Spring 2024
  • Begin Construction - May 2024
  • Substantial Construction Completion - Fall 2024
  • Assessment Hearing Open House - Fall 2024
  • Assessment Hearing - Fall 2024
  1. Bixby Way
  1. Corcoran Path & Dawson Way Area
  1. Delano Way & Dempsey Way Area
  1. Inver Grove Trail (Pine Bend)
  1. South Grove Area 7

Stay Connected

Questions

Project staff appreciates your patience during these construction projects. If you have questions or concerns, please feel free to contact the Project Manager: