Project Timeline

  • Summer 2025 - Data Collection and information Gathering
  • Summer 2025 - Spring 2026 - Draft Feasibility Report
  • Spring 2026 - City Council Meeting: Receive Feasibility Report Public Hearing to consider ordering project
  • Summer 2026 - Winter 2026 - Final Design
  • Spring 2027 - Fall 2027 - Construction open House and Project Construction
  • Fall 2027 - Assessment Open House and City Council Meeting: Assessment Hearing