Construction Update: Barbara Avenue & 46th Street Area

Formatted HTML message

2025 IGH Pavement Management Initiative - Barbara Avenue & 46th Street Area 

Construction Update

Utility crews will be working Monday (7/21) through Wednesday (7/23) along Bacon Avenue (between 47th and 46th), Bacon Court, and completing watermain installation on 46th Street from Bacon to August Way. Intersection of Bacon and 46th will be closed on Tuesday and residents should expect intermittent access impacts during this time due to deep excavation work in front of their house. On Monday, road crews will begin prepping 47th Street and Barbato Court for paving, which is scheduled to take place on Tuesday. On Wednesday, roadway work will occur at the intersection of Bacon Avenue and 47th Street, which will block access to Bacon Avenue from the south during the day. To finish out the week, crews will be working along Barbara Avenue between 47th Street and the midpoint of the road on Thursday and Friday.

Please note that all work is weather-dependent and subject to change.

City Contact:

Please contact David Ray, Asst. City Engineer by email or call 651-450-2541.

More info at: www.ighmn.gov/pavement

* * * * * * *

If you no longer wish to receive these messages, you may manage your preferences and unsubscribe at any time by visiting: www.ighmn.gov/list.asp?mode=del.

Please note, we will not sell or give your email address to any organization without your explicit permission.

 

Plain text message

2025 IGH Pavement Management Initiative - Barbara Avenue & 46th Street Area

Construction Update:

Utility crews will be working Monday (7/21) through Wednesday (7/23) along Bacon Avenue (between 47th and 46th), Bacon Court, and completing watermain installation on 46th Street from Bacon to August Way. Intersection of Bacon and 46th will be closed on Tuesday and residents should expect intermittent access impacts during this time due to deep excavation work in front of their house. On Monday, road crews will begin prepping 47th Street and Barbato Court for paving, which is scheduled to take place on Tuesday. On Wednesday, roadway work will occur at the intersection of Bacon Avenue and 47th Street, which will block access to Bacon Avenue from the south during the day. To finish out the week, crews will be working along Barbara Avenue between 47th Street and the midpoint of the road on Thursday and Friday.

Please note that all work is weather-dependent and subject to change.

City Contact:
Please contact David Ray, Asst. City Engineer by email:dray@ighmn.gov or call 651-450-2541.

More info at: www.ighmn.gov/pavement

* * * * * * *

If you no longer wish to receive these messages, you may manage your preferences and unsubscribe at any time by visiting: www.ighmn.gov/list.asp?mode=del.

Please note, we will not sell or give your email address to any organization without your explicit permission.

SMS message

PMI Update: Paving on 47th, Barbara Ave S of 47th St, and Barbato Ct is scheduled for Tuesday 7/22. Utility work on 46th St, Bacon Ave and Bacon Ct.