Construction Update: 50th Street Area (Babcock to TH 3)

Formatted HTML message

2025 IGH Pavement Management Initiative - 50th Street Area St (Babcock to TH 3)

Construction Update

This Week (08/25–08/29):

Concrete curb installation was completed along 50th Street. Roadway crews continued preparing the surface for pavement.

Next Week (09/02–09/06):

  • 09/02: Final grading and tolerancing on 50th Street
  • 09/03: First layer of pavement on 50th Street
  • 09/04: Pavement reclamation on Ashley Road
  • 09/05: Second asphalt layer on 50th Street
  • 09/06: Begin topsoil placement and restoration

City Contact:

Please contact David Ray, Asst. City Engineer by email or call 651-450-2541.

More info at: www.ighmn.gov/pavement

* * * * * * *

If you no longer wish to receive these messages, you may manage your preferences and unsubscribe at any time by visiting: www.ighmn.gov/list.asp?mode=del.

Please note, we will not sell or give your email address to any organization without your explicit permission.

 

Plain text message

2025 IGH Pavement Management Initiative - 50th Street Area St (Babcock to TH 3)
Construction Update

This Week (08/25–08/29):
​Concrete curb installation was completed along 50th Street. Roadway crews continued preparing the surface for pavement.​​

Next Week (09/02–09/06):
​09/02: Final grading and tolerancing on 50th Street
09/03: First layer of pavement on 50th Street
09/04: Pavement reclamation on Ashley Road
09/05: Second asphalt layer on 50th Street


City Contact:
Please contact David Ray, Asst. City Engineer by email or call 651-450-2541.

More info at: www.ighmn.gov/pavement

* * * * * * *

If you no longer wish to receive these messages, you may manage your preferences and unsubscribe at any time by visiting: www.ighmn.gov/list.asp?mode=del.

Please note, we will not sell or give your email address to any organization without your explicit permission.

SMS message

This week: Curb done, road prepped on 50th St. Next week: paving 9/3 & 9/5, reclaim Ashley 9/4, start restoration 9/6.