2025 IGH Pavement Management Initiative - 50th Street Area St (Babcock to TH 3)
Construction Update
This Week (07/28-08/01):
Utility crews worked on storm sewer along 50th Street and road crews did curb removals in preparation of new curb.
Next Week (08/04-08/09):
50th Street will closed to through traffic start next Thursday morning between the Ashley lane intersections. Access to Ashley Lane will remain open from both directions on 50th St. Utility crews will continue to work on storm sewer work along 50th Street. Expect impacts to traffic and watch out for construction. Be aware of signs posted along roads and please adhere to them.
City Contact:
Please contact David Ray, Asst. City Engineer by email or call 651-450-2541.
More info at: www.ighmn.gov/pavement
* * * * * * *