Bacardi Avenue & 88th Street (Project #2025-09G)

Pavement Management landing page banner that says "Paving a brighter future"

This project is still in the preliminary planning phase.  Click here to review the project area map.

Previous Project Email Notifications:

2025 Pavement Management General Information

Bacardi Avenue & 88th Street Documents

Project Timeline

  • Public Hearing - Monday, August 12, 2024, at 6 p.m. (City Council Chambers, City Hall – 8150 Barbara Ave.)
  • Final Plan Completion - Winter 2024
  • Pre-Construction Open House - Spring 2025
  • Begin Construction - June 2025
  • Substantial Construction Completion - Fall 2025
  • Assessment Hearing Open House - Fall 2025
  • Assessment Hearing - Fall 2025

Stay Connected

Questions?

  • Project Manager, City Engineer Paul Merchlewicz at 651-450-2572 or email.
  • Construction Inspector: TBD